Limited access pond desilting and dredging project

This project in Essex entailed taking our dredging equipment down a very narrow passage, which many contractors cannot do. On the site we had to protect tree roots on some trees that had prevention of damage orders on them.

Prior to beginning the dredging work, the project was surveyed because there wasn’t enough room to put the extracted material on site in a conventional manner because of the levels of the terrain. Also totally removing the silt off sight was too costly for the owner.

So, we came up with a plan of putting some of the material on shore and then the majority was placed behind geo-textile fabrics to create an underwater stepped structure. The owner had to loose some of the area of the pond, but it allowed us to make the depth of the central area of the pond deeper than it otherwise would have been.

For this project, we used a combination of silt pumping and conventional dredging.

The client was very pleased with the result!

Alton Towers Onamental Pond

Recently we were contracted to desilt the Ornamental Pagoda Pond at Alton Towers.

Because of difficult access to the site, we were the only choice for the them.

This project involved using micro pontoons to remove weed from the lake, using conventional dredging methods, to move the material to side of the lake, from where it was transported by dumper to another part of the park for composting.

We then desilted the lake around the edges using our silt pumping methods to move the silt to a different part of the park.

Milton Park, Cambridgeshire, lake clearing and desilting

The main criteria desilting project was to not make any mess at all, as it is a very well kept estate. Because of this requirement, and that our working area was at the far end of the lake but had to be carried out from the water as the client did not want any machinary operating on that part of the shore. So all our desilting equipment had to be manouvered through a small gate and then floated across the lake.

A this end of the lake there were reed beds extending out 9 – 10 meters from the shore of the lake.

From our pontoon, we dredged within the lake, removing the reeds depositing them onto the pontoon and then dropping them off at an agreed spot on the shore where they could be removed for composting.

Once the reeds had been removed, we silt pumped the area, with our pipework floating across the lake (around 150 – 200 meters) and then we pumped the material into a tanker. The tanker itself could not ‘suck’ the silt as the material was too dense.

The other reason for using a tanker was because the client had no immediate area to deposit the silt and we could not use any other method to remove the silt. Once the tanker was full, it removed the silt to an out-of-sight area on the estate where the silt could be deposited.

At the end of the project the customer was extremely pleased because there was no mess, or damage to the grounds, and you couldn’t tell we’d been there.

During the project we pumped in the region of 300 tonnes of silt from the lake.

Royal Vopak Fire Lake, West Thurrock cleaning and desilting

The fire lake (one amongst several) is there to provide water to the West Thurrock Oil Terminal. As you can imagine, for such a critical application, as much water as possible would be needed in an emergency and this particular lake had silted up over time, because it is regualrly topped up by pumping fresh water straight from the river Thames, and therefore it’s water capacity had reduced quite considerable.

As the terminal is live and has fuel tankers coming and going all day long, the client didn’t want a desilting crew interfering with those operations, so all of our operations were conducted from outside the terminal boundary.

Conventional dredging on this project was impossible because of the proximity of buildings and a working oil terminal!

So with only one point of access, our silt pumping system was the only option left open. But even that cuase difficulties as all our equipment had to be craned onto pontoons and from there we did our desilting operations, floating our pipe across the fire lake, through the single access point and out into a nearby field, where the silt was deposited.

Across the whole lake the silt was around 1 meter deep. By removing the silt, the capacity of the lake was increased by approximately 220 gallons per cubic metre.

Norwich area lake desilting

At this lake near Norwich, the silt build up was on a side of the lake that was not accessible by land.

To remove the silt from that side we used our pontoon and pumping system to pump the silt across the water (through our floating pipe) to the silt deposit area in the woods.

Stately home formal pond cleaning

There are many stately homes around the country that have formal ponds that, just like a natural body of water, will silt up over time – this is one such.

Because of a covering of weed on the side walls of this pond, we initially had to drain it, which was no problem for our pumping system.

We then pressure washed the walls, and using the same pumping system, we the removed the silt from the bottom of the pond.

A beautiful pond restored.

Small Lake in the Cotwolds

This lake in the Cotswolds was choked up with weed and had a large silt build up around the weeds.

All the weed had to be conventionally dregded to remove it and was taken away for composting.

The project then required us to desilt the lake and pump the silt to a nearby field, where it was used for composting, once it had dried out. There wasn’t a lot of topsoil on the field and the farmer was happy to get the nutrient rich silt to replace the topsoil that had been washed off the field in years gone by.

Because of the lay of the field, with dips on either side, we were able to pump the silt to the highest point and let the silt disperse down the field, negating the need for bunding or contaiment of the silt.

Approximately 600 cubic metres of silt was pumped from the lake.

Kane Food Reed Filter Desilting

At Kane Foods, the reed filter bed, filters the solid waste of the manufacturing process. But over time, the reeds had become ‘blocked up’.

The reeds needed to remain in place, so we were contracted to use our silt pump to remove the solids from around the reeds, leaving the reeds in place.

The silt was pumped to tankers to be taken away for composting. Because we didn’t want to fill the tankers with more water than waste, our pumping system was ideal as it pumps upto 80% solids to 20% water.

Wentworth Estate

Contact Us

Please use the form below to contact us about your desilting needs. To help us help you, please include a photograph of your site.